Guidesources read November 25, 2026

How much can a contractor ask for as a down payment in California?

California caps the down payment on a home improvement contract at $1,000 or 10 percent of the contract price, whichever is less, under Business and Professions Code section 7159.5. After that, no payment may run ahead of the work done or materials delivered. Skyline Construction and Remodeling works from written contracts; ask for the payment schedule before signing.

What is the legal limit on a contractor's deposit in California?

Section 7159.5 of the Business and Professions Code sets it: the lesser of $1,000 or 10 percent of the contract amount. It covers every home improvement contract with a contractor who is licensed, or should be, whether that is a general contractor or a single trade such as a roofer or a plumber.

The cap is not hidden in fine print. Section 7159 requires the contract itself to carry a "Downpayment" heading, the amount, and a warning in capital letters in at least 12-point bold type. If the contract you are handed has no such line, ask why.

If a downpayment will be charged, the downpayment shall not exceed one thousand dollars ($1,000) or 10 percent of the contract amount, whichever amount is less.

[1] CSLB, 2026 Contractors State License Law Book

THE DOWNPAYMENT MAY NOT EXCEED $1,000 OR 10 PERCENT OF THE CONTRACT PRICE, WHICHEVER IS LESS.

[1] CSLB, 2026 Contractors State License Law Book

What does "10 percent or $1,000, whichever is less" mean in real numbers?

The two limits cross at a $10,000 contract. Below that, 10 percent is the smaller number. Above it, $1,000 is. So for almost any kitchen, bathroom or addition, the most a contractor can take at signing is $1,000.

  • On a contract under $10,000, the cap is 10 percent of the price.
  • On a contract of $10,000 or more, the cap is $1,000, however large the job.

Can a contractor ask for more up front to order materials?

No. Apart from the down payment, section 7159.5 forbids a contractor to ask for or accept money beyond the value of the work done or the material delivered. The contract has to say so in bold capitals in its payment section.

In practice, "we need half now for materials" is the request you are most likely to hear. If special-order items such as cabinets or windows have a long lead time, the fair answer is a payment due when they arrive at your house, written into the schedule. The same limit applies if a lender is paying the contractor for you: a finance company cannot advance money for work not yet done either.

Except for a downpayment, the contractor shall neither request nor accept payment that exceeds the value of the work performed or material delivered.

[1] CSLB, 2026 Contractors State License Law Book

IT IS AGAINST THE LAW FOR A CONTRACTOR TO COLLECT PAYMENT FOR WORK NOT YET COMPLETED, OR FOR MATERIALS NOT YET DELIVERED.

[1] CSLB, 2026 Contractors State License Law Book

The prohibition prescribed by this paragraph extends to advance payment in whole or in part from any lender or financier

[1] CSLB, 2026 Contractors State License Law Book

Is there any exception to the down payment cap?

One, and it is rare. A contractor that has filed a blanket performance and payment bond approved by the CSLB's registrar is exempt from the down payment cap and the progress payment rules. That status shows on the contractor's license record. If a contractor tells you the cap does not apply to them, look it up before you pay.

With this bond in place, the contractor can ask you for the entire contract amount up front.

[2] CSLB, Contracts and Binding Agreements

Only about two dozen companies have been approved to use them.

[2] CSLB, Contracts and Binding Agreements

How should the payments after the deposit be scheduled?

Section 7159 requires a "Schedule of Progress Payments" in the contract whenever you will pay before the job is finished. Each payment must be a dollar amount tied to a described piece of work. "30 percent at midpoint" does not meet that test; a stated dollar amount due "when rough plumbing and electrical pass inspection" does.

A schedule we would want to see as a homeowner ties payments to things you can check: demolition finished, framing or rough-in inspected by the building department, drywall up, cabinets set, final inspection signed off. Hold the last payment until the final inspection is signed and the small items are done. Before each payment, ask for lien releases from the people who were paid out of the last one; our guide to mechanics liens explains how.

Each progress payment shall be stated in dollars and cents and specifically reference the amount of work or services to be performed and materials and equipment to be supplied.

[1] CSLB, 2026 Contractors State License Law Book

Do not let payments get ahead of the work.

[3] CSLB, What You Should Know Before Hiring A Contractor (13P-078/0824)

Avoid paying in cash.

[3] CSLB, What You Should Know Before Hiring A Contractor (13P-078/0824)

What if a contractor asks for more than the limit?

Say no, and ask for a contract with a down payment and schedule that follow the law. A contractor who will not rewrite it is telling you how the rest of the job will go. Taking an oversized down payment is not a paperwork slip under section 7159.5: it is a misdemeanor, and grounds for CSLB discipline against the license.

If you have already paid more than the cap, do not pay ahead again. Keep the contract, the receipts and a dated note of what was said, and contact the CSLB.

is a misdemeanor punishable by a fine of not less than one hundred dollars ($100) nor more than five thousand dollars ($5,000), or by imprisonment in a county jail not exceeding one year

[1] CSLB, 2026 Contractors State License Law Book

From our own jobs

What our clients have written about paying us

The clearest accounts are from 2012. One client paid a $1,000 deposit at signing and then paid at stages as the work was finished; another wrote that he paid for each part of the job after it was completed. These describe past jobs, not a promise of terms: the schedule for your job is written into your contract, and you can ask Eric to go through it with you before you sign.

A client, in their own words

We made additional payments at various milestones -- for example, when the demolition was completed, after electrical and plumbing was installed, etc.
Jorge M., Angi, July 2012

Sources

  1. 1CSLB, 2026 Contractors State License Law Bookcslb.ca.gov, read November 25, 2026
  2. 2CSLB, Contracts and Binding Agreementscslb.ca.gov, read November 25, 2026
  3. 3CSLB, What You Should Know Before Hiring A Contractor (13P-078/0824)cslb.ca.gov, read November 25, 2026

The down payment cap is in the CSLB law book; read the current text before you sign or pay.

Want the answer for your house?

Eric comes to see it and writes the estimate himself, permits included. The visit and the written estimate are free.

(888) 216-1885

Please tell us your name.

Please give a phone number with at least 7 digits, so we can reach you.

This email does not look complete. Check it, or leave it empty.

We use your details only to reply about this job. They are never sold or shared. Privacy

Prefer to talk first? Call (888) 216-1885.