What do published figures say a Los Angeles kitchen costs?
The most specific public benchmark we know of for Los Angeles is Zonda's Cost vs Value 2025 report, published on the Journal of Light Construction's website. It prices one defined kitchen per city, which will differ from yours. These are Zonda's figures, not Skyline's prices, and we do not publish a price list of our own.
Zonda lists three kitchen projects for Los Angeles. Read each job description before you hold a bid up against it, because scope is what separates the smallest figure from the largest.
For a sense of how wide real spending runs, the U.S. Census Bureau's 2023 American Housing Survey gives a national median for kitchen remodels. It counts every owner who remodeled, including people who did the work themselves, so it sits far below a contractor-built Los Angeles kitchen.
Minor Kitchen Remodel | Midrange Job Cost: $29,765
Major Kitchen Remodel | Midrange Job Cost: $86,214
Major Kitchen Remodel | Upscale Job Cost: $171,369
Kitchen remodels $8,000
What kitchen is behind those benchmark numbers?
Both of Zonda's midrange kitchens are the same size: 200 square feet with 30 linear feet of cabinets. The minor one keeps the old cabinet boxes and swaps the doors, counters, appliances, sink and floor. The major one replaces the cabinets with semi-custom ones and adds an island. Neither description moves a wall, relocates the sink or range, or adds a beam.
Zonda also says how its costs are built: a fixed markup on labor and materials, which it calls a starting point. A bid from a contractor who carries insurance, pays a supervisor and comes back after the job will not necessarily look like that formula.
In functional but dated 200-square-foot kitchen with 30 linear feet of cabinetry and countertops, leave cabinet boxes in place but replace fronts with new shaker-style wood panels and drawer fronts
Update outmoded 200-square-foot kitchen with functional layout of 30 linear feet of semi-custom wood cabinets, including 3×5-foot island
The cost data in the Cost vs. Value report does include a standard markup of 10% on materials and 10% on labor.
What makes one kitchen cost more than another?
When two kitchens of the same size come in far apart, the difference is almost always one of the items below. Ask every bidder which of them their number assumes.
- Layout: keeping the sink, range and refrigerator where they are is the cheapest kitchen there is. Moving a sink means new drain and vent lines; moving a gas range means new gas pipe.
- Walls: taking out a non-bearing wall is carpentry and drywall. Taking out a bearing wall means a beam, an engineer's calculations and plan check.
- Cabinets: stock, semi-custom and custom boxes differ widely in price for the same run, before hardware and inside fittings.
- Counters and backsplash: the slab, the edge and the number of cutouts all change the fabricator's price.
- Electrical: new circuits for appliances, more outlets along the counters, under-cabinet and ceiling lighting, and sometimes a larger panel.
- Floor: whether the new floor runs into the rooms beside the kitchen, and what is found under the old one.
- The house itself: older Los Angeles houses can hide galvanized pipe, ungrounded wiring or water damage that only shows once the cabinets come out.
small differences in the size or scope of a project, or in the quality of finishes and accessories the homeowner chooses, can dramatically affect the price.
Does moving a wall change the permit as well as the price?
Yes. In the City of Los Angeles, LADBS lists a home kitchen remodel with no structural changes among its express permits, which are issued without plan review. Once the job removes a bearing wall or adds a beam, it is no longer on that list: someone has to draw plans, an engineer usually signs the beam, and LADBS reviews the drawings before it issues the permit.
That adds cost in three places: the drawings and calculations, the plan check fee, and the weeks of waiting while the kitchen is still in use or already torn out. Cities outside LADBS, such as Calabasas or Burbank, run their own counters and their own fees.
Kitchen/bathroom remodel for residential buildings (no structural changes).
What does the City charge for a kitchen permit?
City fees are a small part of a kitchen budget, but they are real and they are separate from construction. LADBS publishes fee schedules for each trade and an online calculator that estimates the total for a given job. Its plumbing schedule, a form dated July 2017 that is still posted, charges per fixture; a kitchen sink appears in both the new-fixture and the replacement columns.
The calculator's own warning is worth taking at its word: the figure is an estimate, and LADBS sets the final fee when the application is filed. A written estimate should say whether permit fees are inside the price or billed to you at cost.
New or altered lighting in a kitchen has to meet the state energy code, according to the California Energy Commission. That usually means efficient fixtures and the controls the code calls for, and it applies only to the lighting you change.
Kitchen Sinks 23.00
The fee amounts calculated using this application are estimates based on the current fee ordinance and are subject to change without notice.
Altered lighting and any newly installed lighting equipment are required to comply with the residential lighting standards
How do you get a real number for your kitchen?
A published figure tells you the size of the decision. Only a visit tells you the price. Before anyone quotes, they should measure the room, open the sink cabinet, look at the panel and ask what you want to change in the layout.
When the estimates come in, check that each one names the cabinet line or grade, the counter material, who buys the appliances and fixtures, any allowances and what happens if they are exceeded, whether permit fees are included, and how hidden damage will be priced. Two bids that differ on those lines are not comparable, whatever their totals say.
The CSLB's advice is to get at least three written bids on the same plans and scope, and to be wary of the lowest one instead of taking it automatically.
At the local level, the best course of action is to obtain construction cost estimates from reputable local remodelers
Get at least three written bids on your project, and make sure you're comparing bids based on identical plans, specifications, and scope of work.
Do not automatically accept the lowest bid.
From our own jobs
How we price a kitchen
We do not publish kitchen prices, because we would be guessing at a kitchen we have not seen. Eric Saida comes to the house, measures, talks through the layout and writes the estimate himself. Clients have written that the price held to what was agreed, apart from work they added once the job was underway, and that hidden conditions found after demolition were priced as extras.
Kitchen, Woodland HillsWalnut kitchen, Los AngelesKitchen, primary bath and floors, Tarzana