What sets the length of a kitchen remodel?
The construction weeks are only the middle of it. A kitchen runs in a fixed order, and each step waits on the one before. The time you lose is almost always before demolition, in decisions and orders, or between steps, waiting on a delivery or an inspection.
The usual order:
- Design and selections: layout, cabinets, counters, appliances, fixtures, tile and lighting, all decided before work starts.
- Ordering: cabinets and anything special-order go in first, because they have the longest lead times.
- Permit: same day for most kitchens in the City of Los Angeles; longer if plans are needed.
- Demolition and rough-in: the old kitchen comes out, and new plumbing, gas and electrical go into the open walls.
- Rough inspection, then insulation where walls are open, drywall and paint.
- Cabinets, then counters: the counter fabricator measures the installed cabinets before cutting the slab.
- Backsplash, fixtures, appliances, lighting and trim, then the final inspection.
How long does the LADBS permit take for a kitchen?
For most kitchens in the City of Los Angeles, the permit is not what holds you up. LADBS lists a home kitchen remodel with no structural changes as an express permit, issued through its online PermitLA system or at the counter without plan review.
Cities with their own building departments, such as Burbank, Glendale or Calabasas, run their own process, so ask what your city requires before you set a start date.
Kitchen and bathroom remodels for residential buildings with no structural changes are express permits.
The permit can be issued right away - online or in person - with no waiting for plan review.
What if the kitchen moves a wall?
Opening a kitchen to the family room by removing a bearing wall takes it off the express list. Someone draws plans, an engineer sizes the beam, and LADBS checks the drawings before issuing the permit. A small job can sometimes be checked at the counter in a day; a larger one goes to regular plan check, where corrections come back and the plans go in again.
Plan for that before demolition starts. If plan check is needed, the drawings should be approved before the old kitchen comes out, so you are not living without a kitchen while the City reviews.
Counter review is quick when it fits. LADBS says the projects it checks at the counter are small and medium ones it can review in about 45 to 60 minutes.
The plans are reviewed the same day as plan submittal.
The plans are reviewed and then returned within weeks depending on workload.
The types of plans that are typically reviewed at the counter are small and medium size projects that can be reviewed in approximately 45 – 60 minutes.
How do inspections fit into the schedule?
Inspections are fixed points in the schedule. Nothing can be covered until the rough work is signed off, so drywall waits on the inspector, and cabinets wait on drywall. LADBS's homeowner guide asks for a day's notice and warns that workload can add another day.
If the inspector leaves a correction notice, the item is fixed and the inspection is called for again. Every return visit is time the next trade cannot start, which is why the person running the job should be there when the inspector comes.
Call for rough inspection of the construction when all framing work has been completed and the plumbing piping, electrical wiring, and heating ducts have been installed in the framing, but before any of the work has been covered.
Occasionally office workloads delay inspections an additional 24 hours.
What usually makes a kitchen run long?
Most of these are avoidable with decisions made early and written into the contract. Ask your contractor which of them they see most often, and what their schedule assumes about each.
- Selections made late: a faucet or tile chosen after demolition holds up the trade waiting for it.
- Long-lead items: custom cabinets, special-order appliances and some stone slabs.
- Changes once work has started: moving an outlet is quick, moving a sink after the rough-in is not.
- Hidden conditions: rotted subfloor, old galvanized pipe or wiring that has to be replaced before the walls close.
- Inspection corrections, each of which means fixing the item and calling the inspector back.
- Counters: the slab cannot be cut until the cabinets are in, so a cabinet delay moves the counters too.
How do you plan a kitchen around school, holidays or guests?
Work backward from the date that matters. Leave margin for the final inspection and punch list, then count back the construction weeks your contractor gives you, then the cabinet lead time, and that is when every selection has to be made. If the date is a holiday, remember that suppliers and the City keep holiday hours too.
Set up a temporary kitchen somewhere else in the house: the refrigerator, a microwave, a kettle and a folding table. Ask for the schedule in writing, with the days the water or power will be off, and with the inspection dates marked as the points it depends on.
From our own jobs
What our clients have reported
We do not quote a typical kitchen time, because the clients' own numbers are few and mostly old. Clients have written that their kitchens took three weeks from demolition to moving back in (Malisa K., Yelp, 2022), four weeks for a custom kitchen in Tarzana (David W., Yelp, 2012, describing 2011), about five weeks (Mitch P., Yelp, 2014) and about 45 days, which that client put down to delays from city inspections (Rob F., Angi, 2013). Eric Saida sets out a timetable for your own kitchen when he writes the estimate.