Which kind of plan check will my project get?
LADBS sorts projects by how much reviewing they need, and the track sets the clock. Work with no drawings to review, such as a kitchen remodel that leaves the walls alone, skips plan check altogether as an express permit. Everything else goes to one of three plan check tracks.
Counter plan check is for simple projects. On the residential side, the LADBS page lists a one-story addition to a house or duplex, an alteration to a house or duplex, a one-story accessory building built to the Type V sheet, a deck and a low retaining wall without a soil report. Expanded counter plan check takes the next size up, which for homeowners means a medium-sized addition. Regular plan check is for the large and complex, such as a new house.
Your designer or engineer should be able to tell you which track the plans are drawn for before they are finished. Ask, because it changes your calendar more than anything else on this page.
Permits for modest projects like multi-floor tenant improvements, medium-sized home additions and others that require a plan check.
Permits for large complex projects are issued through a Regular Plan Check process.
How long does counter plan check take?
Counter plan check is the fast lane. The plans are looked at while you wait, at one of five LADBS offices, and a short project can leave with corrections marked or approved the same day.
The minutes LADBS quotes are for the review itself rather than your whole trip from drawings to permit. If the reviewer marks corrections, the plans go back to the designer and you return. If other departments need to sign off, their clearances come on top. Expanded counter plan check is also reviewed over the counter, but LADBS says those plans are first assigned within a few days.
Once an expanded counter review starts, LADBS's homeowner step-by-step page says it typically takes two hours or less.
The plans are reviewed the same day as plan submittal. The types of plans that are typically reviewed at the counter are small and medium size projects that can be reviewed in approximately 45 – 60 minutes.
Permits can be issued over the counter through an Expanded Counter Plan Check (ECPC) process.
It will typically take 2 hours or less for your plans to be checked.
How long does regular plan check take?
This is where most of the waiting happens, and LADBS does not put a number on it. Its page says plans are assigned to a plan check engineer within a few days and come back within weeks, depending on how busy the department is. Anyone who quotes you an exact plan check time for a regular review is guessing.
The first review is usually not the last. The engineer returns a list of corrections, the designer answers them, and the plans go back for another look. Plan for at least one round of that, and treat a first approval with no corrections as good luck.
The plans are reviewed and then returned within weeks depending on workload.
Plans are assigned within a few days of submittal.
Can I pay LADBS to speed up plan check?
Yes, for regular plan check. Paying half again of the plan check fee buys an expedited review. It is a surcharge on the plan check fee alone, leaving the rest of the permit fees as they are.
What it buys is a faster review; it does not buy an approval. The page does not say how much faster, and expediting does not answer the corrections for you. If the drawings are incomplete, an expedited review simply tells you so sooner. It earns its cost when the set is complete and the calendar matters, such as when a tenant, a loan or a move-in date is waiting on the permit.
With 50% more of the plan check fee paid, the plan check review will be expedited.
What makes plan check take longer?
Most delay comes from the drawings, not the department. The usual causes are missing sheets, distances to the property lines that are not shown, structural details without the engineer's calculations, and an energy compliance form left out. Each one is a correction, and each correction is another round.
The second cause is other departments. Depending on the lot and the work, City Planning, Fire, Public Works or the Department of Water and Power, among others LADBS lists, may need to approve the project before LADBS issues the permit. LADBS tells you which clearances apply once you file, so ask early whether your lot is likely to need any.
What helps is a complete set the first time, a written answer to every item on the correction sheet, and everything resubmitted at once rather than piece by piece.
They may approve the plans or ask for modifications to be made.
You usually do not arrange these in advance - when you apply, LADBS reviews your project and tells you which clearances are required.
Does submitting online through ePlanLA change the timing?
ePlanLA is the City's online plan submission system. It saves the trips to a counter and lets you see where the review stands, but LADBS does not promise that an online submission is reviewed any faster than a paper one.
For a new detached ADU, a City pre-approved standard plan can shorten review. Our guide to building an ADU explains how that works.
The entire plan check process will be done electronically, including verification and permit issuance.
How should I plan the calendar around plan check?
Do not order cabinets, book trades or give notice on a rental until the permit is issued. LADBS ties the start of construction to the permit, and anything built ahead of approved plans may have to change if the plans do.
Use the waiting time for decisions that do not depend on the permit: choosing tile, fixtures and appliances, and confirming lead times. That way the job can start the week the permit arrives instead of waiting on a showroom.
After you obtain a permit, construction work can begin.
From our own jobs
How it has gone on our jobs
We file the plans and follow them through plan check for our Los Angeles clients, and six reviewers say we obtained or handled their permits. Not every one went smoothly; one client wrote about obstacles with the City, and how they were cleared.
We do not publish a plan check time of our own. The permit records attributed to us show when a permit was applied for and when it was finaled, but not how much of that span was spent in review, so they cannot answer this question honestly.