First, find out what your lot allows
Start with the zoning. In the City of Los Angeles that means LADBS, which can tell you the zone and any specific plan that applies to your address.
Due to the complexity of zoning laws, the only accurate way to obtain the zoning requirements for your proposed building or addition is to visit the Zoning counter in any of the Department’s Construction Service Centers.
Then decide the size
Cities can set their own size limits, but state law stops them from setting the maximum too low.
maximum unit size requirements must allow an ADU of at least 850 square feet of interior livable space, or 1,000 square feet of interior livable space for ADUs with more than one bedroom.
A setback of no more than four feet from the side and rear lot lines shall be required for an attached or detached ADU
Choose custom plans or a standard plan
You can have plans drawn for your lot, or start from a plan the City has already reviewed. A standard plan still has to be fitted to your site.
The City's pre-approved standard plans are only for new, detached ADUs. Converting a detached garage or another existing structure needs plans drawn for that building.
Using standard plans shortens the time needed to review the plans through plan check, and corresponding permits are issued more quickly.
If you choose an approved plan, LADBS will review it to make sure it fits your property, following zoning codes and foundation needs.
No. These pre-approved ADU Standard Plans are only for new, detached structures.
File the plans and wait for a decision
Once the application is complete, state law gives the City 60 days to approve or deny an ADU on a lot that already has a house. Smaller units also avoid impact fees.
There is an earlier deadline too. The City has 15 business days to tell you in writing whether the application is complete. If it misses that, state law treats the application as complete.
An ADU is exempt from incurring impact fees from local agencies, special districts, and water corporations if it contains 750 square feet of interior livable space or less.
An ADU permit application is “deemed complete” when the permitting agency fails to make a timely written completeness determination within 15 business days
Build, pass inspections, finish
Construction runs in inspected stages: foundation, framing, rough electrical and plumbing, insulation, drywall, and final. The unit can be lived in once the final inspection is signed off.
The paperwork that confirms it is the certificate of occupancy. LADBS issues it once the final inspection is approved and the clearances other City departments require, such as sewer and fire access, have been approved too.
Separate plumbing, electrical, and heating permits are required for those installations that are unrelated to the building permit.
The Certificate of Occupancy will be issued by the LADBS after the final inspection is approved and the required clearances from other city departments have been approved.
From our own jobs
What the public record shows for one of ours
A City of Los Angeles permit attributed to our license on BuildZoom converted an 18 by 20 foot detached garage into an ADU, with a 7 by 20 foot addition. The application number dates from 2022 and the permit was finaled on May 1, 2024. That span covers design, plan check and construction together, so it is not a construction time.