The drawings LADBS asks for
The Department's homeowner guide lists the minimum set. In practice a designer or engineer draws them; you should still know what is in the package, because each drawing answers a question the plan checker will ask.
LADBS's current bulletin on the documents for an addition to a house goes further than the homeowner guide. It asks for a full set of structural calculations, for vertical and lateral loads, signed by an engineer or architect licensed in California, and for energy calculations and forms under Part 6 of Title 24 covering the new work.
Who may draw the set is a separate question. California's Architects Practice Act leaves wood-frame single-family houses of up to two stories and a basement outside the architect requirement, so a designer can prepare them. Any part that departs from conventional wood framing has to be designed by a licensed architect or engineer, and the building official will ask for it.
- Plot plan of the building on the lot
- Floor plan of the proposed work
- Framing plan showing the size and spacing of all structural members
- Foundation plan, with floor-framing details
- Elevations of new buildings or additions
- Construction details for rafters, joists and studs
- Energy conservation details, such as insulation thickness
Plans must be clear, legible, and correctly show the work to be done.
If the construction was designed by an engineer, design calculations and plans stamped & signed by the engineer must be attached to the plans.
1. A complete set of Structural Calculations (for vertical and lateral loads) signed by a licensed engineer or architect in the State of California
2. Energy Calculations and Forms for new elements (Part 6 of Title 24)
(1) Single-family dwellings of woodframe construction not more than two stories and basement in height.
the building official having jurisdiction shall require the preparation of plans, drawings, specifications, or calculations for that portion by, or under the responsible control of, a licensed architect or registered engineer.
What the plans must show about the lot
Most addition plans that come back from plan check come back over distances. Show them.
On a hillside lot there is one more step before the plans are final. Where the Baseline Hillside Ordinance applies, LADBS sends you to City Planning for a Joint Referral Form, which sets the most floor area the house may have once the addition is built.
Make sure your plans show all measurements to property lines.
If your construction is attached to an existing building, show the existing room sizes and window and door sizes for the areas adjacent to the new construction.
The BASELINE HILLSIDE ORDINANCE No. 184,802, applies to this project.
Obtain and complete the Joint Referral Form from City Planning to determine the permitted maximum Residential Floor Area.
Where the plans go
Plans are submitted to an LADBS plan check counter. For the west San Fernando Valley the nearest is Van Nuys; the Westside's is on Sawtelle Boulevard in West Los Angeles.
The Department engineers will check your plans for compliance with local codes and ordinances.
Ideas versus plans
Search results for “home addition plans” are mostly floor-plan ideas. Those are useful for deciding what you want: a primary suite on the ground floor, a second story, a family room off the kitchen. They are not permit plans. Permit plans are drawn to your lot, your existing house and its structure, and they are what lets the addition be inspected and recorded.
From our own jobs
An addition we built, from the street
The Culver City second floor on our projects page is a full addition from start to finish: the one-story house on day one, the new floor in timber framing, and the finished bedrooms, landing and bathroom.

(888) 216-1885