HawthorneMay 2024 to June 2025

An ADU and a second unit in Hawthorne, from dirt to occupancy

Skyline Construction built this two-storey building, with an ADU and a second unit, behind an existing house in Hawthorne. The City of Hawthorne issued the permit on May 16, 2024. Digging started June 29, and the certificate of occupancy is dated June 30, 2025. Both kitchens have light oak cabinets and quartz waterfall counters.

Hawthorne, 2025. Living room to kitchen in one of the two new units.

What we built

A new two-storey wood-frame building on a slab, set behind a one-storey house that was already on the lot. It holds two dwelling units. The City of Hawthorne's certificate of occupancy calls them "ADU & the Second unit", lists the occupancy as R-3 and the construction type as V-B, and is dated June 30, 2025.

Inside there are two kitchens with light oak slab-door cabinets and white quartz counters with waterfall ends, walk-in showers in fluted wood-look porcelain, tub-showers behind fixed glass, wood-look plank floors and recessed lights. Upstairs a covered balcony is floored in large porcelain tile. Two heat-pump condensers, two meters and a tankless water heater serve the building.

The job file

City
Hawthorne, Los Angeles County
Built
Permit issued May 16, 2024; certificate of occupancy June 30, 2025
Work
A new two-storey wood-frame building on a slab, behind an existing one-storey house, holding an ADU and a second unit
City record
Permit classed Building (Residential), Accessory Structure. Certificate: occupancy R-3, construction type V-B
Systems
Two heat-pump condensers, two electric meters and a tankless water heater
Inspections
Rough framing needed re-inspection three times before it passed on October 24, 2024. Fire final signed July 2, 2025
Photographs
20 on this page, dated from July 2024 to July 2025
Not on file
The address, the permit number and the owner's name, left out for privacy. The price, which is not on file. A review: none is tied to this job.

How did the foundation go in?

The permit, classed by the city as an accessory structure, was issued on May 16, 2024. The footing trench was dug with a mini excavator on June 29, and wood forms were braced around the whole footprint by July 3.

On July 8 the underground electrical and the plumbing trenches went in inside the forms. In the site video from that morning, a voice off camera says they were "preparing everything for the foundation work". By July 15 the plumbing stubs stood up out of the trenches. The footing inspection on July 24 was a partial pass, and on July 27 the slab was poured: concrete pumped from a truck at the curb over a rebar mat and a plastic vapour barrier.

How long did framing and its inspections take?

Walls were laid out and stood up on the slab on August 1. By August 16 the second floor was framed, and a walk-through video names each space as it stood in bare studs: a shower, vanity and toilet, a laundry room, a linen closet, a closet and a kitchen.

Floor joists and sheathing passed on August 12. Rough framing did not pass the first time: the city asked for re-inspection twice on August 12 and again on October 22, and it passed on October 24. By then the wiring, pipes, ducts and shower supply lines were in the open walls.

What happened between closing the walls and the cabinets?

Insulation passed on November 7, 2024, lath on November 12 and drywall on November 21. The stucco scratch coat passed on December 2 and the brown coat on December 11.

On the balcony, a waterproof membrane went over the plywood on December 20 and a mortar bed was floated on December 21, ready for tile. The showers were tiled by December 23 with two niches each and a hexagon mosaic floor. From December into January a new sewer line was trenched along the side yard and across the front yard.

How did the units get finished?

The oak cabinets and islands were set on January 30 and 31, 2025, without counters. By February 18 the quartz was in, with waterfall ends and a full-height backsplash, and the two condensers were on the side wall. Outside, the side yard got artificial turf, concrete stepping pads, path lights and a white vinyl fence.

The certificate of occupancy is dated June 30, 2025, and the Los Angeles County Fire final was signed off by hand on July 2: about twelve months from the first dig to occupancy.

The dated record

  1. Permit issued by the City of Hawthorne (Building, Residential; Accessory Structure)
  2. Footing trench dug
  3. Footing forms set around the footprint
  4. Underground electrical and plumbing trenches
  5. Plumbing stubs up
  6. Footing inspection: partial pass
  7. Slab poured
  8. Walls stood up on the slab
  9. Floor joists and sheathing passed; rough framing re-inspection required (twice)
  10. Second floor framed; narrated walk-through
  11. Rough framing re-inspection required
  12. Rough framing passed
  13. Insulation passed
  14. Exterior and interior lath passed
  15. Drywall passed
  16. Stucco scratch coat passed
  17. Stucco brown coat passed
  18. Balcony waterproof membrane; side-yard trench
  19. Showers tiled
  20. Sewer line in the trench
  21. Cabinets and islands set
  22. Quartz counters in; condensers on the wall
  23. Certificate of occupancy
  24. Los Angeles County Fire final

Finished

Two-storey stucco building with a gable roof, a covered entry on braced posts and a white vinyl fence
The finished stucco and the covered entry.
Galley kitchen with light oak slab cabinets, a tall pantry, stainless refrigerator and range, and a marble-look quartz waterfall counter
Pantry, fridge and range down one wall, the waterfall counter across from them.
Kitchen peninsula with a white quartz top and waterfall end, light oak cabinets, stainless range and refrigerator
July 17, 2025. A peninsula kitchen with the same oak and quartz.
Walk-in shower behind frameless glass with fluted wood-look tile and two niches, oak vanity with a quartz top and black fixtures
The tiled shower from December, finished: glass, black fixtures, oak vanity.
Tub-shower with a fixed glass panel and wood-look tile wall, beside a long oak vanity under a black-framed mirror
The other bath type: a tub-shower behind a fixed glass panel.
Covered second-floor balcony floored in large grey porcelain tile, with a solid parapet wall and treetops beyond
The balcony from December, finished in large porcelain tile.
Side yard with a covered concrete patio, artificial turf, concrete stepping pads, path lights and a white vinyl fence
The side yard: turf, stepping pads and path lights to the door.

While it was built

Wood footing forms braced around a rectangular trench outlining the whole footprint of the new building
July 3, 2024. Footing forms set around the whole footprint.
Plumbing pipes standing up out of trenches inside the footing forms, before the slab
July 15, 2024. Plumbing stubs up through the trenches, before the slab.
Steel rebar grid on chairs over a clear plastic vapour barrier, inside wood forms with blue clamps
July 27, 2024, before the pour: rebar on chairs above the plastic sheet.
Stud walls framed and stood up on the new concrete slab, with palm trees beyond
August 1, 2024. The first walls go up on the slab.
Open stud walls with electrical boxes, wiring, plumbing and a duct, before insulation
October 15, 2024. Wiring, pipes and ducts in the open walls, nine days before framing passed.
Shower corner framed in wood with red and blue PEX supply lines and a drain in the floor
October 21, 2024. A shower framed and plumbed before the walls close.
Black waterproof membrane rolled over the plywood floor of the second-floor balcony
December 20, 2024. Waterproof membrane on the balcony floor.
Shower walls tiled in fluted wood-look porcelain with two recessed niches, valve still taped
December 23, 2024. Shower walls tiled, two niches, the valve still taped.
Two-storey building in grey brown-coat stucco with a covered entry, behind a white vinyl fence
January 25, 2025. The new building in its brown coat of stucco.
New sewer pipe laid in a deep trench with a vertical cleanout
January 27, 2025. The new sewer line in its trench.
Light oak kitchen cabinets and an island installed without counters, floor covered with protection paper
January 30, 2025. Cabinets and island set, counters still to come.
Kitchen island with a white quartz waterfall end and a full-height quartz backsplash, floor protection still down
February 18, 2025. Quartz waterfall island and full-height backsplash in place.

Where these facts come from

Written up by Skyline Construction and Remodeling on from the records above. Photographs are of this job only. Location data has been removed from every file, and house numbers, number plates and people are cropped or blurred.

Planning something like this in your house?

Eric comes to see the house and writes the estimate himself. The visit and the written estimate are free.

(888) 216-1885

Please tell us your name.

Please give a phone number with at least 7 digits, so we can reach you.

This email does not look complete. Check it, or leave it empty.

We use your details only to reply about this job. They are never sold or shared. Privacy

Prefer to talk first? Call (888) 216-1885.