HawthorneMay 2024 to June 2025
An ADU and a second unit in Hawthorne, from dirt to occupancy
Skyline Construction built this two-storey building, with an ADU and a second unit, behind an existing house in Hawthorne. The City of Hawthorne issued the permit on May 16, 2024. Digging started June 29, and the certificate of occupancy is dated June 30, 2025. Both kitchens have light oak cabinets and quartz waterfall counters.
Hawthorne, 2025. Living room to kitchen in one of the two new units.
What we built
A new two-storey wood-frame building on a slab, set behind a one-storey house that was already on the lot. It holds two dwelling units. The City of Hawthorne's certificate of occupancy calls them "ADU & the Second unit", lists the occupancy as R-3 and the construction type as V-B, and is dated June 30, 2025.
Inside there are two kitchens with light oak slab-door cabinets and white quartz counters with waterfall ends, walk-in showers in fluted wood-look porcelain, tub-showers behind fixed glass, wood-look plank floors and recessed lights. Upstairs a covered balcony is floored in large porcelain tile. Two heat-pump condensers, two meters and a tankless water heater serve the building.
The job file
- City
- Hawthorne, Los Angeles County
- Built
- Permit issued May 16, 2024; certificate of occupancy June 30, 2025
- Work
- A new two-storey wood-frame building on a slab, behind an existing one-storey house, holding an ADU and a second unit
- City record
- Permit classed Building (Residential), Accessory Structure. Certificate: occupancy R-3, construction type V-B
- Systems
- Two heat-pump condensers, two electric meters and a tankless water heater
- Inspections
- Rough framing needed re-inspection three times before it passed on October 24, 2024. Fire final signed July 2, 2025
- Photographs
- 20 on this page, dated from July 2024 to July 2025
- Not on file
- The address, the permit number and the owner's name, left out for privacy. The price, which is not on file. A review: none is tied to this job.
How did the foundation go in?
The permit, classed by the city as an accessory structure, was issued on May 16, 2024. The footing trench was dug with a mini excavator on June 29, and wood forms were braced around the whole footprint by July 3.
On July 8 the underground electrical and the plumbing trenches went in inside the forms. In the site video from that morning, a voice off camera says they were "preparing everything for the foundation work". By July 15 the plumbing stubs stood up out of the trenches. The footing inspection on July 24 was a partial pass, and on July 27 the slab was poured: concrete pumped from a truck at the curb over a rebar mat and a plastic vapour barrier.
How long did framing and its inspections take?
Walls were laid out and stood up on the slab on August 1. By August 16 the second floor was framed, and a walk-through video names each space as it stood in bare studs: a shower, vanity and toilet, a laundry room, a linen closet, a closet and a kitchen.
Floor joists and sheathing passed on August 12. Rough framing did not pass the first time: the city asked for re-inspection twice on August 12 and again on October 22, and it passed on October 24. By then the wiring, pipes, ducts and shower supply lines were in the open walls.
What happened between closing the walls and the cabinets?
Insulation passed on November 7, 2024, lath on November 12 and drywall on November 21. The stucco scratch coat passed on December 2 and the brown coat on December 11.
On the balcony, a waterproof membrane went over the plywood on December 20 and a mortar bed was floated on December 21, ready for tile. The showers were tiled by December 23 with two niches each and a hexagon mosaic floor. From December into January a new sewer line was trenched along the side yard and across the front yard.
How did the units get finished?
The oak cabinets and islands were set on January 30 and 31, 2025, without counters. By February 18 the quartz was in, with waterfall ends and a full-height backsplash, and the two condensers were on the side wall. Outside, the side yard got artificial turf, concrete stepping pads, path lights and a white vinyl fence.
The certificate of occupancy is dated June 30, 2025, and the Los Angeles County Fire final was signed off by hand on July 2: about twelve months from the first dig to occupancy.
The dated record
- Permit issued by the City of Hawthorne (Building, Residential; Accessory Structure)
- Footing trench dug
- Footing forms set around the footprint
- Underground electrical and plumbing trenches
- Plumbing stubs up
- Footing inspection: partial pass
- Slab poured
- Walls stood up on the slab
- Floor joists and sheathing passed; rough framing re-inspection required (twice)
- Second floor framed; narrated walk-through
- Rough framing re-inspection required
- Rough framing passed
- Insulation passed
- Exterior and interior lath passed
- Drywall passed
- Stucco scratch coat passed
- Stucco brown coat passed
- Balcony waterproof membrane; side-yard trench
- Showers tiled
- Sewer line in the trench
- Cabinets and islands set
- Quartz counters in; condensers on the wall
- Certificate of occupancy
- Los Angeles County Fire final
Finished







While it was built












Where these facts come from
- Permit and inspections
work classification Accessory Structure; issued 2024-05-16
The City of Hawthorne permit record and inspection history for this job - Certificate of occupancy
This certification is only for ADU & the Second unit.
The City of Hawthorne certificate of occupancy, June 30, 2025 - Foundation
preparing everything for the foundation work
Our site video of July 8, 2024 - Framing walk-through
We have a laundry room. We have a linen. We have a closet
Our site video of August 16, 2024 - Dates of each stageThe dates on our own site photographs and videos, July 2024 to July 2025
Written up by Skyline Construction and Remodeling on from the records above. Photographs are of this job only. Location data has been removed from every file, and house numbers, number plates and people are cropped or blurred.