What do public figures say a garage conversion costs?
We know of no public-sector source that prices garage conversions in Los Angeles on their own. The nearest is the 2021 statewide survey of ADU owners by UC Berkeley's Terner Center and Center for Community Innovation. It covers every kind of ADU, new detached units included, and the figures are what owners reported spending; they are not Skyline's prices.
A conversion starts with a slab, walls and a roof that are already standing. Whether they can be kept, and how much of them has to be rebuilt to meet the code for a place to live, is the first thing we look at on site, and it moves the price more than anything else.
The median statewide construction cost of an ADU is $150,000, or $250/square foot (sf).
A significant portion of new ADUs (37 percent) cost less than $100,000 to build, and 71 percent of ADUs cost less than $200,000 to construct.
What does LADBS require to turn a garage into living space?
A garage was built to park a car. LADBS's ADU bulletin sets out what it has to become to be lived in: a ceiling high enough, an emergency escape opening, smoke alarms, heat, and energy-code compliance for all the new work. Each of those is a line in the estimate.
Ceiling height is worth checking first. An older garage with low rafters or a sloping floor may need the floor or the roof framing changed to reach the minimum, which is a different job from adding drywall.
A minimum ceiling height of 7 feet shall be provided throughout.
All new work done to convert or permit existing unpermitted buildings or portions of buildings to an ADU(s) or JADU shall comply with California Building Energy Efficiency Standards (Title 24- Part 6).
Which parts of an old garage usually drive the cost?
Every garage we look at gets the same questions. The answers decide whether a conversion is mostly finish work or mostly rebuilding.
Some of the old garage can usually stay. LADBS lets existing foundations remain if they are in good condition, and the old garage door header too.
In a methane zone, keeping the slab helps as well. A conversion is spared the City's methane mitigation rules as long as the existing slab stays undisturbed and has only hairline cracks.
- The slab: whether it is level, cracked or sitting low against the driveway, and whether the new floor will be built up over it.
- The foundation and walls: whether the footing can carry the new work, whether the walls are anchored to it, and how much framing has to be added for insulation and windows.
- The garage door opening: it has to be framed in as a wall, usually with a window or door, and finished to match the outside.
- The roof: whether it can take insulation and a finished ceiling, and whether it leaks.
- Utilities: the distance to the sewer line for a bathroom or kitchen, whether the electrical panel has room for the new circuits, and how the unit will be heated and cooled.
- Position on the lot: a garage close to the property line needs fire-rated walls, which changes the wall build.
Newly conditioned space must comply with the requirements for an addition.
The ground surface plane in the reduced clearance area shall be surfaced with a concrete slab at least three inches in thickness.
Existing foundation components are allowed to remain in place provided that they are in good condition and comply with the conventional construction requirements at the time the building was built or any other time.
Existing garage door headers are permitted to remain.
Existing buildings located in a Methane Buffer Zone or a Methane Zone shall not be required to comply with LABC Chapter 71 Methane Mitigation, provided the existing slab remains undisturbed and has only hairline cracks.
Do walls near the property line or fire sprinklers add cost?
Many Los Angeles garages sit a few feet from a side or rear fence. LADBS requires fire-resistance rated walls at that distance, which means a particular drywall and assembly on the walls that face the neighbor.
Sprinklers are less common than owners fear. The state housing department says a conversion needs them only if the main house is itself required to have them. If the house is getting a major remodel at the same time, ask whether that changes the answer before you sign.
Exterior walls less than 5 feet from the property line of a non-sprinklered ADU(s) or JADU conversion or less than 3 feet from the property line of a sprinklered ADU(s) or JADU conversion shall be 1-hour fire-resistance rated construction.
Installation of fire sprinklers shall not be required in ADUs or JADUs if sprinklers are not required by building standards for the existing primary residence.
Which fees apply to a garage conversion, and which are waived?
State law and the City between them waive several fees that a new house would pay. LADBS's bulletin lists the City fees an ADU does not pay. The state housing department adds that a unit made from existing space is not treated as a new home when utilities set connection charges, and that small units escape school fees.
What remains are LADBS's own plan check and permit fees, fees for the separate electrical, plumbing and mechanical permits, and, for a unit over 500 square feet, the school district's fee. Size the unit with those thresholds in mind; a few square feet can decide whether a fee applies.
There is a size line for impact fees too. State law waives them for an ADU of 750 square feet of interior livable space or less.
ADUs and JADUs are exempt from Park Fees (LAMC 12.33) and Affordable Housing Linkage Fee (LAMC 19.18).
ADUs constructed from existing space and JADUs shall not be considered by a local agency, special district, or water corporation to be a new residential use for purposes of calculating connection fees or capacity charges for utilities
ADUs and JADUs that are less than 500 square feet of interior livable space are not subject to school impact fees.
An ADU is exempt from incurring impact fees from local agencies, special districts, and water corporations if it contains 750 square feet of interior livable space or less.
What costs come before construction starts?
Budget for the work that happens on paper. The state housing department's handbook, describing a grant program whose funds it says are now used up, lists the costs it counted as predevelopment. They are a fair checklist for any conversion: drawings, permits, sometimes a soils test or a survey, and the energy report.
Ask each bidder whether design, engineering and the energy report are inside their price or separate. On a conversion these can be a meaningful share of the total, and they are paid before anyone picks up a hammer.
Predevelopment costs include, but are not limited to, architectural designs, permits, soil tests, impact fees, property surveys, and energy reports.
From our own jobs
How we price a conversion
We do not publish a conversion price. Eric Saida looks at the slab, the framing, the roof, the panel and the route to the sewer, then writes the estimate himself, and we manage the permit and inspections. A City of Los Angeles permit attributed to our license turned an 18 by 20 foot detached garage into an ADU with a small addition; its permit valuation is a fee figure set for the City rather than what the owner paid, so we do not quote it as a price.