How long does plan review take in Pasadena?
It turns on whether the project fits Pasadena's over-the-counter thresholds. Simple work can be reviewed at the Permit Center in minutes; anything more complex goes behind the counter and waits its turn, about two to four weeks a round. New construction, ADUs and additions have to be filed online through the city's Citizen Self Service portal, while some small jobs, such as a service upgrade or a water heater, may need no plans at all.
Budget for three rounds. The city says a typical project goes in three times, the first set and two revisions, and asks for a complete set up front to keep that number down. If a revision changes the square footage, the permit fees are recalculated to match.
Simple projects that meet our over-the-counter thresholds can be reviewed over the counter in as little as 5 to 10 minutes.
Typically, projects will average three (3) plan submissions (one initial submission and two revisions).
In some cases, plans are not necessary for some work (e.g., upgrading electrical service, replacing a water heater).
What does a contractor need to pull a Pasadena permit?
A state license, a City of Pasadena business license and workers' compensation insurance, and the city checks the license with the Contractors State License Board when the permit is issued. Contractors based outside Pasadena can buy a business license for three months, six months or a year. Owners can pull their own permits, but an owner who then hires unlicensed workers has to carry workers' compensation for them. The permit and inspection card stay posted on site for the inspectors.
If you are a contractor you must present a valid contractor license and a current City of Pasadena business license
Additionally, property owners who obtain permits and then hire unlicensed workers will be required to provide Workers’ Compensation Insurance and are subject to other liabilities.
What are Pasadena's ADU rules and fee breaks?
Pasadena's current ADU and junior ADU rules are in Ordinance No. 7420, in effect since May 20, 2024. The city runs an ADU Standard Plans program of pre-approved designs from studios to two-bedroom units, and it is strict about them: a standard plan cannot be changed at all, however small the change.
Fees are where the choice pays off. On a single-family lot, an ADU of 900 square feet or less is exempt from the residential impact fees, and building from a standard plan halves the plan check fee and waives several permit fees too. The reductions are not retroactive, so confirm which ones apply before you pay.
Updated regulations for Accessory Dwelling Units (ADUs) and Junior ADUs went into effect on May 20,2024.
Modifications to pre-approved ADU plans are not allowed, regardless of how minor the changes are.
Fee reductions are not retroactive.
How long does plan check take in Culver City?
About three to four weeks of working days. The Building Safety Division posts that plan checks are running 15 to 20 business days, counted from payment and routing rather than from the day you apply. Electrical, mechanical and plumbing permit fees are charged when you apply, under the fee schedule that took effect on March 14, 2025.
Paper revisions go in the drop-off bin outside the division's second-floor offices at City Hall and sit for two to three days before processing; small ones may be handled by email. Inspections are requested by email with the permit number and address, and can be done in person or by video call. Every contractor needs a current Culver City business license.
Please Note: All plan checks are running approximately 15-20 business days from the date of payment and routing.
Plans and applications will sit for approximately 48-72 hours for sanitization prior to processing.
Inspections may be conducted in person or virtually via FaceTime or Cisco Webex Meet
Contractors will be required to have a current Culver City business license
How long do Culver City applications and permits stay valid?
An application is treated as abandoned 12 months after it is filed, with extensions of up to 90 days each. Once issued, a permit lapses if work does not start within 12 months, or if it stops for 180 days. Extensions of up to 180 days are possible but may bring conditions, extra fees or new permits. A slow design phase and a long pause mid-job both cost money here.
An application for a permit for any proposed work is deemed abandoned 12 months after the application date.
Every permit issued shall become invalid unless the work on the site authorized by such permit is commenced within 12 months after its issuance, or if the work authorized on the site by such permit is suspended or abandoned for a period of 180 days after the time the work is commenced.
Does Culver City have pre-approved ADU plans?
Yes, for newly built units: a 468 square foot studio, a 637 square foot one-bedroom and an 806 square foot two-bedroom, each in three styles. You still need a site plan for your lot and a building permit, and plan check and development impact fees still apply. For an ADU built without permits before January 1, 2020, the city advises a confidential code inspection by a licensed contractor before you apply to legalize it.
The plans are available in PDF format in three different layouts (studio, 1 bedroom, 2 bedroom) and three different styles, Post-War Bungalow, Spanish Revival, and Contemporary.
No construction is permitted without an approved Building Permit. All applicable plan check and development impact fees still apply.
Is Valencia or Stevenson Ranch in Santa Clarita?
Valencia is. When Santa Clarita incorporated in 1987 it took in Saugus, Newhall, Valencia and Canyon Country, and dozens of neighborhoods have been annexed since. Stevenson Ranch is an unincorporated community governed by the County, so its permits come from Los Angeles County Building and Safety. Check the parcel before you hire anyone to draw.
In 1987, the City of Santa Clarita became the largest area to incorporate in the state of California. At just 39 square miles back then, the new City included the communities of Saugus, Newhall, Valencia and Canyon Country.
Instead, governance and representation are provided by the Los Angeles County Board of Supervisors
How does plan review work in Santa Clarita?
Projects that need no more than half an hour of review, small residential remodels, patio covers, sheds, pools and spas among them, can usually be reviewed at the Permit Center in City Hall during morning counter hours. Larger work needs full plans, and for most project types the city wants them prepared by a California licensed architect or engineer.
Two things slow people down. Every applicable agency's clearance has to be in hand before the city issues the permit, and getting them is your job. Larger projects can pay for expedited review, which the city says cuts the turnaround in half.
Smaller projects which require no more than 30 minutes for plan review can typically be reviewed over-the-counter, during morning counter hours only, at the City’s Permit Center located in City Hall, Suite 140.
For most project types, the plans must be prepared by a California Licensed Architect or Engineer.
Clearances from all of the applicable agencies must be obtained before Building & Safety can issue a building permit.
Plan review services for projects over $100,000 in valuation may be expedited. The fee for expedited plan review is an additional 50% of the plan review fee.
Who gets the permit and books inspections in Santa Clarita?
The city puts the duty on the property owner, though in practice your contractor usually pulls the permit. Inspections are requested on the city's 24-hour hotline by early afternoon on the working day before. Some residential jobs can be permitted online at once, among them main panel upgrades, water heater change-outs, repipes and water service lines. The city is replacing its older PVA instant permits with MEP permits through Symbium from May 1, 2026, and any PVA permit not finaled by May 1, 2027 will need a new MEP permit.
Before a building is constructed, repaired, or altered, the property owner is responsible to obtain the necessary permits.
To schedule an inspection of work being done under an active City Permit, call the inspection request hotline prior to 2:30 p.m. one working day prior to the day of the inspection.
From our own jobs
What we have built in these places
In Culver City we added a full second floor to a one-story house, finished by August 2017, with framing, stucco, central air, wiring, a bathroom and hardwood floors. In Pasadena we remodeled a kitchen with a farm sink, an island and marble counters; our own Yelp caption names the city, posted in 2011. Just outside Santa Clarita, in unincorporated Stevenson Ranch, we remodeled the primary and guest bathrooms of a home in 2019 for a household we had worked for twice before.
Second-floor addition, Culver CityPrimary and guest bathrooms, Stevenson Ranch
(888) 216-1885