What does LADBS treat a second story as?
As a structural addition, which puts it in plan check from the start. There is no express permit and no same-day route for building up. An engineer or architect prepares the drawings and calculations, they go to LADBS through ePlanLA, and a plan check engineer reviews them before anything is built.
Plan check is only part of the approval. LADBS lists zoning, sewer and drainage as the likely clearances for a second story, and other departments can be added depending on the lot. The permit is ready only once the plans and every clearance have been signed off. Our guide to LADBS plan check times covers how long that usually takes.
California's Energy Code treats it as an addition too, because it adds conditioned floor area and volume. The new rooms have to meet the energy rules for additions, which our guide to Title 24 for remodels explains.
Adding a second story is a structural addition that requires engineered plans through ePlanLA.
Drafted plans will be reviewed for code compliance and required clearances will be confirmed before the permit is issued.
RTI stands for "Ready to Issue," which means your plans and all clearances have been approved.
An addition is any change to an existing building that increases both conditioned floor area and conditioned volume (including conditioning a previously unconditioned space).
How much floor area will the zoning let me add?
On most single-family lots in the City of Los Angeles, the Baseline Mansionization Ordinance caps the total Residential Floor Area of the house. The cap depends on the zone and the size of the lot, and the rooms you already have count toward it. Building up saves yard space, but the new upstairs rooms still use up the same allowance as ground-floor rooms would.
So the first number to find is how much of the allowance your house already uses. For smaller additions LADBS asks for the County Assessor's record of the existing floor area. The zone of your lot is on ZIMAS, City Planning's online map. If the drawings go over the limit, the plan checker sends them back with a correction citing the ordinance, and the design has to shrink before a permit is issued. Have the designer run the floor-area numbers before anyone draws a staircase.
Provide copy of most recent Los Angeles County Tax Assessor's records to verify existing Residential Floor Area for additions with cumulative area less than 1,000 sq. ft. which are subject to Baseline Mansionization Ordinance.
The proposed project exceeds the maximum Residential Floor Area
How tall can the house be with a second floor?
The limit is set by your zone and height district, and the plans have to prove the house stays under it. The elevations show the height in feet and in stories, measured from the grade plane to the top of the roof, and on a sloping lot a topographic map may be needed to establish that grade.
Roof shape matters more than people expect. A steep pitched roof on top of a new floor can be what pushes a design over the limit, and a basement with a habitable room counts as a story for the height district. We give no single figure here because the limit differs by zone; your designer reads it for your lot before the massing is fixed.
Show maximum height of the structure (in feet and stories) from top of roof to grade plane on all elevation views.
Building exceeds ( ) height limit for ( ) zone.
Basement containing a habitable room shall be considered a story for side and rear yard and Height District's requirements.
What changes if my lot is in the hills?
Hillside lots have a second set of rules, the Baseline Hillside Ordinance, with its own floor-area and grading limits. LADBS may ask for the type of street in front of the lot to be confirmed with Public Works, and where the ordinance applies, City Planning fills in a Joint Referral Form that sets the maximum floor area. That form and a slope analysis map become part of the approved plans.
If you are in the Santa Monica Mountains, the hills above Studio City or another sloping neighborhood, ask early whether your lot falls under it, because it can change what size of second story is possible.
The HILLSIDE ORDINANCE may apply to this project.
Obtain and complete the Joint Referral Form from City Planning to determine the permitted maximum Residential Floor Area.
Will my foundation hold a second floor?
That is the engineer's first question, and LADBS makes it a plan-check question too. The footings under a one-story house were sized for one story. Once a second floor sits on them, the existing footings carry new loads and have to meet the code for them, which can mean enlarging footings or adding new ones under the walls that will take the weight.
The second load is sideways. An engineer or architect designs the system that resists earthquake and wind forces, and on a second-story job that usually reaches down into the ground floor: new shear walls, hold-downs bolted into the foundation and connections between the old walls and the new floor. Expect some ground-floor walls to be opened up for it, even if the rooms downstairs are otherwise staying as they are. Who may draw which part of the plans is covered in our guide on whether you need an architect.
Existing footings supporting new loads shall also comply.
Provide design by a licensed engineer or architect for the (vertical) (seismic/wind lateral) force resisting system
Shear wall and hold-down details, including wall construction, nailing, anchor bolts, transfer connections, and hold-downs for new construction
What if my house is outside the City of Los Angeles?
Then LADBS is not your building department, and the floor-area and height rules above do not apply as written. Culver City, Santa Monica, Burbank, Glendale and the unincorporated county each run their own permits, plan check and inspections, with their own zoning codes. The structural questions stay the same anywhere: an engineered design, footings checked for the new load, and lateral bracing from the roof down. Our guide on which building department issues your permit sorts out who you deal with.
We accomplish this through permitting, plan check, and inspection services.
From our own jobs
A second floor we built in Culver City
Our documented second-story job is in Culver City, finished by August 2017. The house started as a single-story stucco home, and the new floor was built on top of it while the home was lived in. We framed the new floor in timber, framed a stair up from the ground floor, then wrapped the upper walls and finished them in stucco to match the walls below, with clay-colored roof tile to match.
Upstairs the owners gained bedrooms with French doors onto arched balconies, a walk-in closet, central air and a bathroom with a jetted tub and a separate shower. The project page shows it from the day the job moved in to the finished rooms. What our records do not hold is the job's length, its price or its permit number, so we do not quote them.
(888) 216-1885